Project Cost Performance Index Calculator
Compare earned value with actual cost to assess cost performance.
Compare earned value with planned value to measure schedule performance in budget-value terms. The result is not a delay measured in days, and both inputs must describe the same status date.
Compare budgeted value earned from completed work with work planned by a project status date. Schedule variance measures the gap in budget-value units, while the schedule performance index expresses their ratio.
Select one project scope and status date. Completed and planned work need comparable budget valuation before either subtraction or division can produce a meaningful comparison.
Subtract planned value from earned value. A negative amount means less budgeted work has been earned than planned; a positive amount means more has been earned.
Divide earned value by positive planned value. One means the values match. With zero planned value, variance remains calculable but the ratio is undefined.
Sample inputs demonstrate the method. They are not a forecast or product offer.
Earned value of €80,000 against €100,000 planned value gives a variance of minus €20,000. The ratio is 0.8, meaning earned budget value is 80% of the planned amount at that date.
Sample inputs demonstrate the method. They are not a forecast or product offer.
Variance uses the project's budget currency. It cannot directly give days late because planned work and its budget value are not necessarily distributed evenly through time.
An index below one indicates less earned work than planned at this status point. It does not forecast completion, identify the critical path or measure the cost incurred to do that work.
No. Translating earned-value variance into time requires the baseline schedule and the distribution of planned work.